Creating a Project Network Diagram
Dec 15,2006 00:00
by
admin
Creating a Project Network DiagramRecall that a WBS is a topology of the project deliverables. A WBS takes the project and breaks the project down into major components. These components can then be broken down again into other components, then again into work packages, and, finally, documented with a task list that is derived from the WBS. Once the WBS has been created, the activity list can then be entered into Microsoft Project, or your favorite Project Management Information Systems (PMIS) software . Once you enter the activities into Microsoft Project, you can create a Gantt chart like the one in Figure 7-2. It shows a mapping of each of the units of work required to complete each phase of the project. The Gantt chart is ideal for simple, short-term projects. It is a timeline of the events with consideration given to tasks that can be completed concurrently within a project’s lifespan. Traditional Gantt charts have some drawbacks:
To address these issues, project managers can use a Project Network Diagram (PND). PNDs are a fluid mapping of the work to be completed. Figure 7-3 is a sample of a portion of a network diagram. Incidentally, the terms “PND,” “Project Network Diagrams,” and “network diagrams” all refer to the same workflow structure—don’t let the different names confuse you. Such diagrams allow the project manager and the project team to tinker with the relationships between tasks and create alternative solutions to increase productivity, profitability, and the diligence of a project. A PND visualizes the flow of work from conception to completion. Network diagrams provide detailed information on work units and allow project managers to analyze tasks, resources, and the allotted time for each task. You can use a PND to determine the flow of work to predict the earliest completion date. Network diagrams are ideal for these situations:
Utilizing the Precedence Diagramming MethodYou could start the PND by mapping out work units on a whiteboard, like you did for the WBS—which is a fine method. However, rather than creating a flat timeline of activity, project managers can use the Precedence Diagramming Method to create a fluid project structure. This sophisticated approach stems from the 1950s, when the original concept was called the activity-on-the-arrow (AOA) method. As you can see in Figure 7-4, each arrow represents a task in the project. The origin of the arrow is the “begin activity” sign, and the end of the arrow is the “end activity” sign. As you can imagine, this representation of a project, especially a large project, could prove very cumbersome, as project managers can only have very simple relationships between tasks. What replaced the AOA method is the activity-on-the-node (AON) method. With the AON method, the focus is on the activities rather than on the start and end of activities. This methodology of creating a network diagram is also called the Precedence Diagramming Method (PDM). PDM requires the project manager to evaluate each work unit and determine which tasks are its successors and which tasks are its predecessors. Once this information is obtained, you can begin to snap the pieces of the PDM puzzle together. You must give careful consideration to the placement of each task, as all tasks are connected even if they are scheduled to run concurrently. Each unit of work in a network diagram using PDM is represented by a rectangle called the activity node. Predecessors are linked to successors by arrows, and are always upstream from successors, as Figure 7-5 demonstrates. One work unit can be both a successor and a predecessor; for example, the task to install and configure a web server may first require the installation of an operating system; only after the web server task is complete can the web pages the web server will host be added. To begin creating the network diagram using PDM, a project manager will have to determine the order of tasks to be completed. Basically, a project manager asks, “What tasks must be completed before the next tasks can begin?” The activity list, which you derived from your WBS work packages, is what you are sequencing. You do not want activities that are too short in length to be useful. Based on your project, you may have work units that last days or weeks—generally not hours. A rectangular box represents each individual task within the network diagram. As you add tasks to the network diagram, draw an arrow between tasks to connect them in the successor/predecessor relationship. As expected, the network diagram is read left to right, top to bottom. Each task within the diagram must have a successor and predecessor—except for the first and last task in the project. Once the diagram has been completed with successor and predecessor tasks, it is considered a “connected network.” A project manager, or anyone involved in the project, can trace any activity through the network. The relationship between activities is what allows a project to move forward or to wait for other tasks to complete. An accurate description between tasks is required for the project manager to analyze and make adjustments to each task in the network diagram. Figure 7-6 shows the dependency types you may have between tasks. There are four types of dependencies:
|