The
Central Limit Theorem Applied to Networks
Take notice that the critical path through the network always
connects the beginning node or milestone and the ending node or milestone. The
ending milestone can be thought of as the output milestone, and all the tasks in
between are input to the final output milestone. Furthermore, if the project
manager has used three-point estimates for the task durations, then the duration
of any single task is a random variable best represented by the expected value
of the task. [2] The total duration
of the critical path from the input or beginning milestone to the output
milestone, itself a 0-duration event, or the date assigned to the output
milestone, represents the length of the overall schedule. The length of the
overall schedule is a summation of random variables and is itself a random
variable, L, of length:
L = Σ Di
= (D1 +
D2 +
Di ...)
where Di are
the durations of the tasks along the critical path.
We know from our discussion of the Central Limit Theorem that for
a "large" number of durations in the sum the distribution of L will tend to be Normal regardless of the distributions
of the individual tasks. This statement is precisely the case if all the
distributions are the same for each task, but even if some are not, then the
statement is so close to approximately true that it matters little to the
project manager that L may not be
exactly Normal distributed. Figure
7-8 illustrates this point.