 Sections
Syndication |
|
|
|
|
Rebaselining the Performance Measurement Baseline
Rebaselining the
Performance Measurement Baseline
The time may arise when the PMB no longer represents the
plan that the project team is working to complete and the variances being
reported are therefore not meaningful. In that event, the project manager, in
consultation with the project sponsor, will rebaseline the project. Some rules
should be decided in advance regarding how rebaselining is to be done. The
following are the usual steps:
-
Make a clear demarcation of the scope that is to be
baselined in the second baseline.
-
For the scope in the first baseline, set
EVbaseline1 = PVbaseline1. All unearned planned value goes
to the second baseline and applies to the scope moved to the second baseline.
Note that setting the planned value equal to the earned value at the end of PMB
1 resets the schedule and value variance to $0. The cost variance remains
unchanged in PMB 1 and for the project as a whole.
-
The planned value moved to the second baseline is then
decomposed into a second WBS and a second PMB is fashioned. The second WBS does
not need to be structured the same as the first WBS, but the scope that moves
should be mapped from WBS1 to
WBS2.
616
times read
|
|
|
|
|