Super Business - Project Management Articles


Sections
Syndication



Preparing the Project Team for Earned Value


Preparing the Project Team for Earned Value

From the bicycle example and the equations presented in Table 6-4, it is somewhat evident what must be done to prepare the project team for earned value. The most critical steps are:

  • Prepare a complete WBS for the project. Without a complete WBS, the PMB cannot be adequately prepared. Earned value is measurement of accomplishment against a baseline. Without the baseline, there can be no meaningful measurement. In the chapter on estimates, we discussed in detail how to decompose the sponsor's value estimate into the WBS. In the earned value system, the sponsor's value estimate becomes the planned value of the project.

  • Set up the project rules for sizing the cost accounts work packages. Work packages are the smallest units of work on the WBS and are collectively rolled into cost accounts. Cost accounts are typically the lowest level on the WBS where formal cost tracking and allocation are made. Sizing the cost account means deciding how large in dollars a cost account should be before it is too large for effective management and needs to be subdivided into multiple cost accounts. There are no fixed rules. On some smaller projects, $50,000 or less may be a cost account; however, on larger projects, so small an amount may be impractical. The project manager and the project team make these decisions.

  • Provide a means to collect and report actual cost. Collecting and reporting actual cost is the most difficult part of applying earned value. Outside of the contractor community that serves the Department of Defense, there are few businesses that invest in the means to collect actual cost beyond direct purchases. Most projects are run with salaried labor for which project-level timekeeping is not available. Without actual cost, there is little that can be done with the quantitative metrics of earned value, although the concept of focusing on accomplishment remains valid.

  • Set up the project rules for claiming earned value credit. Earned value credit rules must be set up in advance and made known to the cost account and work package leaders.


187 times read

Related news

» Project Cost Management
by admin posted on Aug 26,2010
» Analogous Estimating
by admin posted on Aug 26,2010
» What is the difference between estimated cost and price
by admin posted on Oct 06,2010
» Cost Control
by admin posted on Aug 26,2010
» What is life cycle cost
by admin posted on Oct 06,2010