Preparing
the Project Team for Earned Value
From the bicycle example and the equations presented in Table 6-4, it is
somewhat evident what must be done to prepare the project team for earned value.
The most critical steps are:
-
Prepare a complete WBS for the project. Without a complete
WBS, the PMB cannot be adequately prepared. Earned value is measurement of
accomplishment against a baseline. Without the baseline, there can be no
meaningful measurement. In the chapter on estimates, we discussed in detail how
to decompose the sponsor's value estimate into the WBS. In the earned value
system, the sponsor's value estimate becomes the planned value of the
project.
-
Set up the project rules for sizing the cost accounts work
packages. Work packages are the smallest units of work on the WBS and are
collectively rolled into cost accounts. Cost accounts are typically the lowest
level on the WBS where formal cost tracking and allocation are made. Sizing the
cost account means deciding how large in dollars a cost account should be before
it is too large for effective management and needs to be subdivided into
multiple cost accounts. There are no fixed rules. On some smaller projects,
$50,000 or less may be a cost account; however, on larger projects, so small an
amount may be impractical. The project manager and the project team make these
decisions.
-
Provide a means to collect and report actual cost.
Collecting and reporting actual cost is the most difficult part of applying
earned value. Outside of the contractor community that serves the Department of
Defense, there are few businesses that invest in the means to collect actual
cost beyond direct purchases. Most projects are run with salaried labor for
which project-level timekeeping is not available. Without actual cost, there is
little that can be done with the quantitative metrics of earned value, although
the concept of focusing on accomplishment remains valid.
-
Set up the project rules for claiming earned value credit.
Earned value credit rules must be set up in advance and made known to the cost
account and work package leaders.