Work Breakdown Structure Baseline
 
Work Breakdown
Structure Baseline
For quantitative estimating purposes, we need a target to
shoot at. It is better that the target be a static target, not moving during the
time of estimation. The scope captured on the WBS at the time estimating begins
is the project "baseline scope." Baselines are "fixed" until they are changed.
Changing the baseline is a whole subject unto itself. Suffice to say that once
resources are assigned to a baseline, and then that baseline is changed, the
task of the project manager and project administrator is to map from the RAM in
the baseline to the RAM of the changed baseline. A common practice is to
consider all resource consumption from initial baseline to the point of
rebaseline to be "sunk cost," or actuals to date (ATD), not requiring mapping.
Expenditures going forward are either mapped from the initial baseline, or the
WBS of the subsequent baseline is re-estimated as "estimate to complete" (ETC).
Total project cost at completion then becomes:
Cost at completion = ATD of WBS Baseline-1 + ETC of WBS
Baseline-2
The practical effect of rebaselining is to reset variances and
budgets on the WBS. The WBS dictionary may also be modified for the new
baseline. Considering the need for cost and performance history, and the
connection to the chart of accounts, there are a couple of approaches that can
be taken. To preserve history, particularly valuable for future and subsequent
estimations, WBS Baseline-1 may be given a different project account number on
the chart of accounts from that assigned to
the WBS Baseline-2. The cost history of WBS Baseline-1 and the WBS Baseline-1
dictionary can then be saved for future reference.
A second and less desirable approach from the viewpoint of
preserving history is to make a lump sum entry into the chart of accounts for
the ATD of WBS Baseline-1. Then WBS Baseline-2 is connected to the chart of
accounts in substitution for WBS Baseline-1 and work begins
anew.
52 times read
|
|
|
|