Integrating the
Project Balance Sheet and Business Value Models
Now let us integrate the concepts discussed in this chapter
to complete the framework on which we hang quantitative analysis to be discussed
in the remainder of this book. The business models drive the left side of the
project balance sheet. The model results, working through the value flow-down
process, frame opportunity (new products, new markets and customers, operational
and organizational needs) and quantify goals. Goals, deployed through strategy,
lead to identified projects. It remains to select among the identified projects
those that are affordable, most beneficial, or of highest priority to the
business. We will discuss decision making in quantitative terms in Chapter 4. Suffice
it to say there is a means to make these selections and charter the project. The
generally accepted definition of the project charter is "a document issued by senior management that formally authorizes the
existence of a project..." [20] More about the charter can be found in the
literature, primarily A Guide to the Project Management Body of
Knowledge. [21] With
charter in hand, the project sponsor conveys
the project requirements and investment allocation to the project manager. Doing
so completes the chain from business executive to project sponsor, thence to
project manager through the connectivity of the project charter and the
left-to-right-side bridging effect of scope on the project balance sheet, as
illustrated in Figure 1-8.
We now have a consistent and traceable path to and from the source
of business value for numbers from the right side of the project balance sheet
representing capability and risk. A traceable path is needed, after all, because
projects draw their value only from the business.
On the right side of the balance sheet we have two elements: (1)
project capability and capacity and (2) risk. A well-accepted method to express
capability and capacity is with the so-called "iron triangle" of scope, time,
and cost. Since there is interdependency among these three, it is traditionally
to set the one of highest priority, optimize the second highest priority
element, and the third becomes what is necessary to close the triangle. This
author prefers the "project four-angle" of scope, schedule, resources, and
quality as shown in Figure 1-9. The set-and-optimize process is about the same
as in the iron triangle, except that two elements could be involved in the
setting or optimizing.
We will see in Chapter 3 that the best quantification tool for scope is the
WBS. Time and cost can be estimated for the scope on the WBS somewhat
independently, but ultimately they are tied together through the concept of
value. Earned value is the preferred numerical analysis tool, and that will be
discussed in Chapter
6. There are numerous ways to evaluate quality. One we will address in Chapter 8 is Six
Sigma.
Finally, there is risk. Risk in quantitative terms is expressed in
the same units as the related item in the project capability and capacity. The
risk component of the right side of the balance sheet holds the variance to the
mean that must be managed in order not to endanger the business investment.
Figure 1-10
illustrates the points discussed.