Project Balance
Sheet Details
The project balance sheet seeks to make a quantitative and
qualitative connection between the business and the project. On the left side,
the business side, is the sponsor's view of the project. The sponsor's view is
conceptual and value oriented, nearly void of facts, or at least void of the
facts as the project manager would understand them. Often the sponsor has no
specific understanding of project management, of cost and schedule estimating
for research and development, or of statistical analysis of risk, and does not
seek to acquire an understanding. In system engineering parlance, the project
sponsor sees the project as a "black box." However, the sponsor knows what the
business requires and knows how much investment can be made toward the
requirements.
The project manager has the facts about the project, even if they
are only rough estimates. The project manager knows and understands the scope,
even if the scope has "known unknowns" that require more investigation and
definition. [18] We have already
made the point that risk balances the facts with the concepts. However, a bridge
is needed to couple unambiguously the sponsor's understanding and the project
manager's understanding of the same project. That bridge between project manager
and business manager is a common understanding of scope. Even with language and
experience barriers, scope is the translator. The test for the project manager
is then to ensure that there is good understanding of scope and then to convey
the risks in business terms. This done, the project charter can be signed with
expectation of good results to come.
Now what about debits and credits? Where do they come into the
project balance sheet? Like the accounting equation, the project equation is not
a functional equation of the form y = f(x) + c that
specifies y to be functionally dependent on x. Indeed, the left and right sides are pretty much
independent, just like in the financial domain. By independent, we mean that the
estimates of cost and schedule done by the project manager are based on the
facts developed by the project team for the work specified in the work breakdown
structure (WBS). Those project team estimates
are not, or should not be, dependent on the business value estimate developed by
the project sponsor. However, once the charter is set, a change in one of the
three elements (business value on the left side, risk or project capability on
the right side) requires that another of the three elements must correspondingly
change to maintain balance.
If, for instance, we continue to say debits are increases to the
left and credits are increases to the right, then a debit of scope by the
sponsor (that is, an increase in scope) must have a corresponding credit on the
right or else balance is violated. By way of another example, if the situation
were that the project manager had to credit the capability, [19] and no debit was available from the
sponsor, then the required debit must go to risk in order to restore
balance.
But is balance really all that important? Yes. The
interpretation of imbalance is that there is not a meeting of the minds
regarding the value demanded (left side) and the likelihood of successful
delivery (right side). Consequently, the project may not be sustained, sponsor
confidence in results may be challenged, and the project team may not be
supported adequately during execution.