Overview
Project Time Management includes the processes required to
accomplish timely completion of the project. Figure 6-1 provides an
overview of the Project Time Management processes and Figure 6-2 provides
a process flow diagram of those processes and their inputs, outputs, and other
related Knowledge Area processes. The Project Time Management processes include
the following:
6.1 Activity Definition – identifying the
specific schedule activities that need to be performed to produce the various
project deliverables.
6.2 Activity Sequencing – identifying and
documenting dependencies among schedule activities.
6.3 Activity Resource Estimating – estimating
the type and quantities of resources required to perform each schedule
activity.
6.4 Activity Duration Estimating – estimating
the number of work periods that will be needed to complete individual schedule
activities.
6.5 Schedule Development – analyzing activity
sequences, durations, resource requirements, and schedule constraints to create
the project schedule.
6.6 Schedule Control – controlling changes to
the project schedule. These processes interact with each other and with
processes in the other Knowledge Areas as well. Each process can involve effort
from one or more persons or groups of persons, based on the needs of the
project. Each process occurs at least once in every project and occurs in one or
more project phases, if the project is divided into phases. Although the
processes are presented here as discrete components with well-defined
interfaces, in practice they can overlap and interact in ways not detailed here.
Process interactions are discussed in detail in Chapter 3.
On some projects, especially ones of smaller scope, activity
sequencing, activity resource estimating, activity duration estimating, and
schedule development are so tightly linked that they are viewed as a single
process that can be performed by a person over a relatively short period of
time. These processes are presented here as distinct processes because the tools
and techniques for each are different.
Although not shown here as a discrete process, the work involved
in performing the six processes of Project Time Management is preceded by a
planning effort by the project management team. This planning effort is part of
the Develop Project Management Plan process (Section 4.3), which produces a
schedule management plan that sets the format and establishes criteria for
developing and controlling the project schedule. The project time management
processes, and their associated tools and techniques, vary by application area,
are usually defined as part of the project life cycle (Section 2.1), and are documented in
the schedule management plan. The schedule management plan is contained in, or
is a subsidiary plan of, the project management plan (introduction to Section 4.3), and
may be formal or informal, highly detailed or broadly framed, based upon the
needs of the project.
|
Note |
Note: Not all process interactions and data flow among the
processes are shown.
|