Overview
The Project Integration Management Knowledge Area includes
the processes and activities needed to identify, define, combine, unify, and
coordinate the various processes and project management activities within the
Project Management Process Groups. In the project management context,
integration includes characteristics of unification, consolidation,
articulation, and integrative actions that are crucial to project completion,
successfully meeting customer and other stakeholder requirements, and managing
expectations. Integration, in the context of managing a project, is making
choices about where to concentrate resources and effort on any given day,
anticipating potential issues, dealing with these issues before they become
critical, and coordinating work for the overall project good. The integration
effort also involves making trade-offs among competing objectives and
alternatives. The project management processes are usually presented as discrete
components with well-defined interfaces while, in practice, they overlap and
interact in ways that cannot be completely detailed in the PMBOKĀ® Guide.
The need for integration in project management becomes evident in
situations where individual processes interact. For example, a cost estimate
needed for a contingency plan involves integration of the planning processes
described in greater detail in the Project Cost Management processes, Project
Time Management processes, and Project Risk Management processes. When
additional risks associated with various staffing alternatives are identified,
then one or more of those processes must be revisited. The project deliverables
also need to be integrated with ongoing operations of either the performing
organization or the customer's organization, or with the long-term strategic
planning that takes future problems and opportunities into consideration.
Most experienced project management practitioners know there is no
single way to manage a project. They apply project management knowledge, skills,
and processes in different orders and degrees of rigor to achieve the desired
project performance. However, the perception that a particular process is not
required does not mean that it should not be addressed. The project manager and
project team must address every process, and the level of implementation for
each process must be determined for each specific project.
The integrative nature of projects and project management can be
better understood if we think of the other activities performed while completing
a project. For example, some activities performed by the project management team
could be to:
-
Analyze and understand the scope. This includes the project
and product requirements, criteria, assumptions, constraints, and other
influences related to a project, and how each will be managed or addressed
within the project.
-
Document specific criteria of the product requirements.
-
Understand how to take the identified information and
transform it into a project management plan using the Planning Process Group
described in the PMBOKĀ® Guide.
-
Prepare the work breakdown structure.
-
Take appropriate action to have the project performed in
accordance with the project management plan, the planned set of integrated
processes, and the planned scope.
-
Measure and monitor project status, processes and products.
-
Analyze project risks.
Among the processes in the Project Management Process Groups, the
links are often iterated. The Planning Process Group provides the Executing
Process Group with a documented project management plan early in the project and
then facilitates updates to the project management plan if changes occur as the
project progresses.
Integration is primarily concerned with effectively integrating
the processes among the Project Management Process Groups that are required to
accomplish project objectives within an organization's defined procedures. Figure 4-1 provides an overview of
the major project management integrative processes. Figure 4-2 provides a process flow diagram of those
processes and their inputs, outputs and other related Knowledge Area processes.
The integrative project management processes include:
4.1 Develop Project Charter - developing the
project charter that formally authorizes a project or a project phase.
4.2 Develop Preliminary Project Scope Statement
- developing the preliminary project scope statement that provides a high-level
scope narrative.
4.3 Develop Project Management Plan -
documenting the actions necessary to define, prepare, integrate, and coordinate
all subsidiary plans into a project management plan.
4.4 Direct and Manage Project Execution -
executing the work defined in the project management plan to achieve the
project's requirements defined in the project scope statement.
4.5 Monitor and Control Project Work -
monitoring and controlling the processes used to initiate, plan, execute, and
close a project to meet the performance objectives defined in the project
management plan.
4.6 Integrated Change Control - reviewing all
change requests, approving changes, and controlling changes to the deliverables
and organizational process assets.
4.7 Close Project - finalizing all activities
across all of the Project Management Process Groups to formally close the
project or a project phase.
|
Note |
Note: Not all process interactions and data flow among the
processes are shown.
|