Risk Management Planning
Careful and explicit planning enhances the possibility of
success of the five other risk management processes. Risk Management Planning is
the process of deciding how to approach and conduct the risk management
activities for a project. Planning of risk management processes is important to
ensure that the level, type, and visibility of risk management are commensurate
with both the risk and importance of the project to the organization, to provide
sufficient resources and time for risk management activities, and to establish
an agreed-upon basis for evaluating risks. The Risk Management Planning process
should be completed early during project planning, since it is crucial to
successfully performing the other processes described in this chapter.
Section
11.1.1 Risk Management Planning: Inputs
.1 Enterprise Environmental Factors
The attitudes toward risk and the risk tolerance of organizations
and people involved in the project will influence the project management plan
(Section 4.3).
Risk attitudes and tolerances may be expressed in policy statements or revealed
in actions (Section
4.1.1.3).
.2 Organizational Process Assets
Organizations may have predefined approaches to risk management
such as risk categories, common definition of concepts and terms, standard
templates, roles and responsibilities, and authority levels for decision-making.
.3 Project Scope Statement
Described in Section 5.2.3.1.
.4 Project Management Plan
Described in Section 4.3.
Section
11.1.2 Risk Management Planning: Tools and Techniques
.1 Planning Meetings and Analysis
Project teams hold planning meetings to develop the risk
management plan. Attendees at these meetings may include the project manager,
selected project team members and stakeholders, anyone in the organization with
responsibility to manage the risk planning and execution activities, and others,
as needed.
Basic plans for conducting the risk management activities are
defined in these meetings. Risk cost elements and schedule activities will be
developed for inclusion in the project budget and schedule, respectively. Risk
responsibilities will be assigned. General organizational templates for risk
categories and definitions of terms such as levels of risk, probability by type
of risk, impact by type of objectives, and the probability and impact matrix
will be tailored to the specific project. The outputs of these activities will
be summarized in the risk management plan.
Section
11.1.3 Risk Management Planning: Outputs
.1 Risk Management Plan
The risk management plan describes how risk management will be
structured and performed on the project. It becomes a subset of the project
management plan (Section 4.3). The risk management plan includes the
following:
-
Methodology. Defines the approaches,
tools, and data sources that may be used to perform risk management on the
project.
-
Roles and responsibilities. Defines the
lead, support, and risk management team membership for each type of activity in
the risk management plan, assigns people to these roles, and clarifies their
responsibilities.
-
Budgeting. Assigns resources and estimates
costs needed for risk management for inclusion in the project cost baseline (Section 7.2.3.1).
-
Timing. Defines when and how often the
risk management process will be performed throughout the project life cycle, and
establishes risk management activities to be included in the project schedule
(Section
6.5.3.1).
-
Risk categories. Provides a structure that
ensures a comprehensive process of systematically identifying risk to a
consistent level of detail and contributes to the effectiveness and quality of
Risk Identification. An organization can use a previously prepared
categorization of typical risks. A risk breakdown structure (RBS) (Figure 11-4) is one approach to
providing such a structure, but it can also be addressed by simply listing the
various aspects of the project. The risk categories may be revisited during the
Risk Identification process. A good practice is to review the risk categories
during the Risk Management Planning process prior to their use in the Risk
Identification process. Risk categories based on prior projects may need to be
tailored, adjusted, or extended to new situations before those categories can be
used on the current project.
Figure 11-4. Example of
a Risk Breakdown Structure (RBS)
-
Definitions of risk probability and
impact. The quality and credibility of the Qualitative Risk Analysis process
requires that different levels of the risks' probabilities and impacts be
defined. General definitions of probability levels and impact levels are
tailored to the individual project during the Risk Management Planning process
for use in the Qualitative Risk Analysis process (Section 11.3).
A relative scale representing probability values from 'very
unlikely' to 'almost certainty' could be used. Alternatively, assigned numerical
probabilities on a general scale (e.g., 0.1, 0.3, 0.5, 0.7, 0.9) can be used.
Another approach to calibrating probability involves developing descriptions of
the state of the project that relate to the risk under consideration (e.g., the
degree of maturity of the project design).
The impact scale reflects the significance of impact, either
negative for threats or positive for opportunities, on each project objective if
a risk occurs. Impact scales are specific to the objective potentially impacted,
the type and size of the project, the organization's strategies and financial
state, and the organization's sensitivity to particular impacts. Relative scales
for impact are simply rank-ordered descriptors such as 'very low,' 'low,'
'moderate,' 'high,' and 'very high,' reflecting increasingly extreme impacts as
defined by the organization. Alternatively, numeric scales assign values to
these impacts. These values may be linear (e.g., 0.1, 0.3, 0.5, 0.7, 0.9) or
nonlinear (e.g., 0.05, 0.1, 0.2, 0.4, 0.8). Nonlinear scales may represent the
organization's desire to avoid high-impact threats or exploit high-impact
opportunities, even if they have relatively low probability. In using nonlinear
scales, it is important to understand what is meant by the numbers and their
relationship to each other, how they were derived, and the effect they may have
on the different objectives of the project.
Figure 11-5 is an
example of negative impacts of definitions that might be used in evaluating risk
impacts related to four project objectives. That figure illustrates both
relative and numeric (in this case, nonlinear) approaches. The figure is not
intended to imply that the relative and numeric terms are equivalent, but to
show the two alternatives in one figure rather than two.
-
Probability and impact matrix. Risks are prioritized
according to their potential implications for meeting the project's objectives.
The typical approach to prioritizing risks is to use a look-up table or a
Probability and Impact Matrix (Figure 11-8 and Section 11.3.2.2). The specific combinations of probability
and impact that lead to a risk being rated as 'high,' 'moderate,' or 'low'
importance-with the corresponding importance for planning responses to the risk
(Section
11.5)-are usually set by the organization. They are reviewed and can be
tailored to the specific project during the Risk Management Planning process.
-
Revised stakeholders' tolerances.
Stakeholders' tolerances may be revised in the Risk Management Planning process,
as they apply to the specific project.
-
Reporting formats. Describes the content
and format of the risk register (Sections 11.2, 11.3, 11.4, and 11.5) as well as any other risk reports required. Defines how
the outcomes of the risk management processes will be documented, analyzed, and
communicated.
-
Tracking. Documents how all facets of risk
activities will be recorded for the benefit of the current project, future
needs, and lessons learned. Documents whether and how risk management processes
will be audited