Create WBS
The WBS is a deliverable-oriented hierarchical decomposition
of the work to be executed by the project team, to accomplish the project
objectives and create the required deliverables. The WBS organizes and defines
the total scope of the project. The WBS subdivides the project work into
smaller, more manageable pieces of work, with each descending level of the WBS
representing an increasingly detailed definition of the project work. The
planned work contained within the lowest-level WBS components, which are called
work packages, can be scheduled, cost estimated, monitored, and controlled.
The WBS represents the work specified in the current approved
project scope statement. Components comprising the WBS assist the stakeholders
in viewing the deliverables (Section 4.4.3.1) of the project.
Section 5.3.2 Create WBS: Tools and
Techniques
.1 Work Breakdown Structure Templates
Although each project is unique, a WBS from a previous project can
often be used as a template for a new project, since some projects will resemble
another prior project to some extent. For example, most projects within a given
organization will have the same or similar project life cycles and, therefore,
have the same or similar deliverables required from each phase. Many application
areas or performing organizations have standard WBS templates.
The Project Management Institute Practice Standard for Work
Breakdown Structures provides guidance for the generation, development, and
application of work breakdown structures. This publication contains
industry-specific examples of WBS templates that can be tailored to specific
projects in a particular application area. A portion of a WBS example, with some
branches of the WBS decomposed down through the work package level, is shown in
Figure 5-6.
.2 Decomposition
Decomposition is the subdivision of project deliverables into
smaller, more manageable components until the work and deliverables are defined
to the work package level. The work package level is the lowest level in the
WBS, and is the point at which the cost and schedule for the work can be
reliably estimated. The level of detail for work packages will vary with the
size and complexity of the project.
Decomposition may not be possible for a deliverable or subproject
that will be accomplished far into the future. The project management team
usually waits until the deliverable or subproject is clarified so the details of
the WBS can be developed. This technique is sometimes referred to as rolling
wave planning.
Different deliverables can have different levels of decomposition.
To arrive at a manageable work effort (i.e., a work package), the work for some
deliverables needs to be decomposed only to the next level, while others need
more levels of decomposition. As the work is decomposed to lower levels of
detail, the ability to plan, manage, and control the work is enhanced. However,
excessive decomposition can lead to non-productive management effort,
inefficient use of resources, and decreased efficiency in performing the work.
The project team needs to seek a balance between too little and too much in the
level of WBS planning detail.
Decomposition of the total project work generally involves the
following activities:
-
Identifying the deliverables and related work
-
Structuring and organizing the WBS
-
Decomposing the upper WBS levels into lower level detailed
components
-
Developing and assigning identification codes to the WBS
components
-
Verifying that the degree of decomposition of the work is
necessary and sufficient.
Identifying the major deliverables of the project and the work
needed to produce those deliverables requires analyzing the detailed project
scope statement. This analysis requires a degree of expert judgment to identify
all the work including project management deliverables and those deliverables
required by contract.
Structuring and organizing the deliverables and associated project
work into a WBS that can meet the control and management requirements of the
project management team is an analytical technique that may be done with the use
of a WBS template. The resulting structure can take a number of forms, such as:
-
Using the major deliverables and subprojects as the first
level of decomposition, as shown in Figure 5-6.
-
Using subprojects as illustrated in Figure 5-6, where
the subprojects may be developed by organizations outside the project team. For
example, in some application areas, the project WBS can be defined and developed
in multiple parts, such as a project summary WBS with multiple subprojects
within the WBS that can be contracted out. The seller then develops the
supporting contract work breakdown structure as part of the contracted work.
-
Using the phases of the project life cycle as the first
level of decomposition, with the project deliverables inserted at the second
level, as shown in Figure 5-7.
Figure 5-7. Sample Work Breakdown Structure
Organized by Phase
-
Using different approaches within each branch of the WBS, as
illustrated in Figure 5-8, where test and evaluation is a phase, the air
vehicle is a product, and training is a supporting service.
Figure 5-8. Sample Work Breakdown for Defense
Materiel Items
Decomposition of the upper level WBS components requires
subdividing the work for each of the deliverables or subprojects into its
fundamental components, where the WBS components represent verifiable products,
services, or results. Each component should be clearly and completely defined
and assigned to a specific performing organizational unit that accepts
responsibility for the WBS component’s completion. The components are defined in
terms of how the work of the project will actually be executed and controlled.
For example, the status- reporting component of project management could include
weekly status reports, while a product to be manufactured might include several
individual physical components plus the final assembly.
Verifying the correctness of the decomposition requires
determining that the lower-level WBS components are those that are necessary and
sufficient for completion of the corresponding higher-level deliverables.
Section 5.3.3 Create WBS: Outputs
.1 Project Scope Statement (Updates)
If approved change requests result from the Create WBS process,
then the project scope statement is updated to include those approved changes.
.2 Work Breakdown Structure
The key document generated by the Create WBS process is the actual
WBS. Each WBS component, including work package and control accounts within a
WBS, is generally assigned a unique identifier from a code of accounts. These
identifiers provide a structure for hierarchical summation of costs, schedule,
and resource information.
The WBS should not be confused with other kinds of breakdown
structures used to present project information. Other structures used in some
application areas or other Knowledge Areas include:
-
Organizational Breakdown Structure (OBS).
Provides a hierarchically organized depiction of the project organization
arranged so that the work packages can be related to the performing
organizational units.
-
Bill of Materials (BOM). Presents a
hierarchical tabulation of the physical assemblies, subassemblies, and
components needed to fabricate a manufactured product.
-
Risk Breakdown Structure (RBS). A
hierarchically organized depiction of the identified project risks arranged by
risk category.
-
Resource Breakdown Structure (RBS). A
hierarchically organized depiction of the resources by type to be used on the
project.
.3 WBS Dictionary
The document generated by the Create WBS process that supports the
WBS is called the WBS dictionary and is a companion document to the WBS. The
detailed content of the components contained in a WBS, including work packages
and control accounts, can be described in the WBS dictionary. For each WBS
component, the WBS dictionary includes a code of account identifier, a statement
of work, responsible organization, and a list of schedule milestones. Other
information for a WBS component can include contract information, quality
requirements, and technical references to facilitate performance of the work.
Other information for a control account would be a charge number. Other
information for a work package can include a list of associated schedule
activities, resources required, and an estimate of cost. Each WBS component is
cross-referenced, as appropriate, to other WBS components in the WBS dictionary.
.4 Scope Baseline
The approved detailed project scope statement (Section 5.2.3.1)
and its associated WBS and WBS dictionary are the scope baseline for the
project.
.5 Project Scope Management Plan (Updates)
If approved change requests result from the Create WBS process,
then the project scope management plan may need to be updated to include
approved changes.
.6 Requested Changes
Requested changes to the project scope statement and its
components may be generated from the Create WBS process, and are processed for
review and approval through the integrated change control process.