Cost Budgeting
Cost budgeting involves aggregating the estimated costs of
individual schedule activities or work packages to establish a total cost
baseline for measuring project performance. The project scope statement provides
the summary budget. However, schedule activity or work package cost estimates
are prepared prior to the detailed budget requests and work authorization.
Section 7.2.1 Cost Budgeting: Inputs
.1 Project Scope Statement
Formal periodic limitations of the expenditure of project funds
can be given in the project charter (Section 4.1.3.1) or contract. These
funding constraints are reflected in the project scope statement, and can be due
to annual funding authorizations by the buyer’s organization or other entities
like government agencies.
.2 Work Breakdown Structure
The project work breakdown structure (WBS) (Section 5.3.3.2) provides the
relationship among all the components of the project and the project
deliverables (Section 4.4.3.1).
.3 WBS Dictionary
The WBS dictionary (Section 5.3.3.3) and related detailed statements of work
provide an identification of the deliverables and a description of the work in
each WBS component required to produce each deliverable.
.4 Activity Cost Estimates
The cost estimates (Section 7.1.3.1) for each schedule activity within a work
package are aggregated to obtain a cost estimate for each work package.
.5 Activity Cost Estimate Supporting Detail
Described in Section 7.1.3.2.
.6 Project Schedule
The project schedule (Section 6.5.3.1) includes planned start and finish dates for
the project’s schedule activities, schedule milestones, work packages, planning
packages, and control accounts. This information is used to aggregate costs to
the calendar periods when the costs are planned to be incurred.
.7 Resource Calendars
Described in Section 6.3.3.4.
.8 Contract
Contract (Section 12.4.3.2) information related to what products,
services, or results have been purchased — and their costs — are used in
developing the budget.
.9 Cost Management Plan
The cost management plan component of the project management
plan and other subsidiary plans are considered during cost budgeting.
Section 7.2.2 Cost Budgeting: Tools and
Techniques
.1 Cost Aggregation
Schedule activity cost estimates are aggregated by work packages
in accordance with the WBS. The work package cost estimates are then aggregated
for the higher component levels of the WBS, such as control accounts, and
ultimately for the entire project.
.2 Reserve Analysis
Reserve analysis (Section 11.6.2.5) establishes contingency reserves, such as
the management contingency reserve, that are allowances for unplanned, but
potentially required, changes. Such changes may result from risks identified in
the risk register
Management contingency reserves are budgets reserved for
unplanned, but potentially required, changes to project scope and cost. These
are “unknown unknowns,” and the project manager must obtain approval before
obligating or spending this reserve. Management contingency reserves are not a
part of the project cost baseline, but are included in the budget for the
project. They are not distributed as budget and, therefore, are not a part of
the earned value calculations.
.3 Parametric Estimating
The parametric estimating technique involves using project
characteristics (parameters) in a mathematical model to predict total project
costs. Models can be simple (e.g., residential home construction will cost a
certain amount per square foot of living space) or complex (e.g., one model of
software development costs uses thirteen separate adjustment factors, each of
which has five to seven points within it).
Both the cost and accuracy of parametric models vary widely. They
are most likely to be reliable when:
-
The historical information used to develop the model is
accurate
-
The parameters used in the model are readily quantifiable
-
The model is scalable, such that it works for a large
project as well as a small one.
.4 Funding Limit Reconciliation
Large variations in the periodic expenditure of funds are
usually undesirable for organizational operations. Therefore, the expenditure of
funds is reconciled with the funding limits set by the customer or performing
organization on the disbursement of funds for the project. Reconciliation will
necessitate the scheduling of work to be adjusted to smooth or regulate those
expenditures, which is accomplished by placing imposed date constraints for some
work packages, schedule milestones, or WBS components into the project schedule.
Rescheduling can impact the allocation of resources. If funds were used as a
limiting resource in the Schedule Development process, then the process is
repeated using the new imposed date constraints. The final product of these
planning iterations is a cost baseline.
Section 7.2.3 Cost Budgeting: Outputs
.1 Cost Baseline
The cost baseline is a time-phased budget that is used as a basis
against which to measure, monitor, and control overall cost performance on the
project. It is developed by summing estimated costs by period and is usually
displayed in the form of an S-curve, as illustrated in Figure 7-5. The
cost baseline is a component of the project management plan.
Many projects, especially large ones, have multiple cost or
resource baselines, and consumables production baselines (e.g., cubic yards of
concrete per day) to measure different aspects of project performance. For
example, management may require that the project manager track internal costs
(labor) separately from external costs (contractors and construction materials)
or total labor hours.
.2 Project Funding Requirements
Funding requirements, total and periodic (e.g., annual or
quarterly), are derived from the cost baseline and can be established to exceed,
usually by a margin, to allow for either early progress or cost overruns.
Funding usually occurs in incremental amounts that are not continuous, and,
therefore, appears as a step function in Figure 7-5. The total funds
required are those included in the cost baseline plus the management contingency
reserve amount. Some portion of the management contingency reserve can be
included incrementally in each funding step or funded when needed, depending on
organizational policies.
Although Figure 7-5 shows the management reserve amount at
the end of the project, in reality, the cost baseline and cash flow lines would
increase when a portion of the management reserve is authorized and when it is
spent. Any gap at the end of a project between the funds allocated and the cost
baseline and cash flow amounts shows the amount of the management reserve that
was not used.
.3 Cost Management Plan (Updates)
If approved change requests (Section 4.4.1.4) result from the Cost
Budgeting process, then the cost management plan component of the project
management plan is updated if those approved changes impact the management of
costs.
.4 Requested Changes
The Cost Budgeting process can generate requested changes (Section 4.4.3.2)
that affect the cost management plan or other components of the project
management plan. Requested changes are processed for review and disposition
through the Integrated Change Control process (Section 4.6).