Risk Monitoring and Control: Tools and Techniques
.1 Risk Reassessment
Risk Monitoring and Control often requires identification of new
risks and reassessment of risks, using the processes of this chapter as
appropriate. Project risk reassessments should be regularly scheduled. Project
Risk Management should be an agenda item at project team status meetings. The
amount and detail of repetition that is appropriate depends on how the project
progresses relative to its objectives. For instance, if a risk emerges that was
not anticipated in the risk register or included on the watchlist, or if its
impact on objectives is different from what was expected, the planned response
may not be adequate. It will then be necessary to perform additional response
planning to control the risk.
.2 Risk Audits
Risk audits examine and document the effectiveness of risk
responses in dealing with identified risks and their root causes, as well as the
effectiveness of the risk management process.
.3 Variance and Trend Analysis
Trends in the project's execution should be reviewed using
performance data. Earned value analysis (Section 7.3.2.4) and other methods of
project variance and trend analysis may be used for monitoring overall project
performance. Outcomes from these analyses may forecast potential deviation of
the project at completion from cost and schedule targets. Deviation from the
baseline plan may indicate the potential impact of threats or opportunities.
.4 Technical Performance Measurement
Technical performance measurement compares technical
accomplishments during project execution to the project management plan's
schedule of technical achievement. Deviation, such as demonstrating more or less
functionality than planned at a milestone, can help to forecast the degree of
success in achieving the project's scope.
.5 Reserve Analysis
Throughout execution of the project, some risks may occur, with
positive or negative impacts on budget or schedule contingency reserves (Section 11.5.2.4).
Reserve analysis compares the amount of the contingency reserves remaining to
the amount of risk remaining at any time in the project, in order to determine
if the remaining reserve is adequate.
.6 Status Meetings
Project risk management can be an agenda item at periodic
status meetings. That item may take no time or a long time, depending on the
risks that have been identified, their priority, and difficulty of response.
Risk management becomes easier the more often it is practiced, and frequent
discussions about risk make talking about risks, particularly threats, easier
and more accurate.