Header
Home | Set as homepage | Add to favorites
  Search the Site     » Advanced Search
Sections
Syndication



Total Number Of Issues Over Time

by

image

 

Total Number Of Issues Over Time

Here you only use the date of discovery of the issue. The x axis is time. On the y axis is the number of issues that have been found as of that point in time. You can also do this chart by type of issue. Figure 10.7 gives an example chart with two international projects. The solid line represents a project that is going well. As time progresses, there are few new issues found. There is a spike toward the end to accommodate the seemingly inevitable hidden issues that surface late in the project. The dotted line is another matter entirely. This is a project in trouble where new issues keep surfacing. Note that this chart says nothing about solving the issues. Nevertheless, it is another indicator of the project state.

Click To expand
Figure 10.7: Total Number of Issues by Date of Discovery

Open Issues over Time

Let’s add the status to the data in the previous chart. You will chart the number of open issues that exist at a particular point in time versus time. Again, you could do this by type of issue as well. Figure 10.8 contains two examples. The solid line for Project A represents a project in which the issues are under control. The dashed line represents a problem project. Note that the number of issues that are open tends to rise and then drop off. It may temporarily pick up and then drop again.

Click To expand
Figure 10.8: Open Issues over Time

This chart is useful in tracking how the project is doing in resolving issues. It also serves as an early indicator of a project in trouble. If the number of open issues is not declining toward the end of the project, it is possible that the project will fail.

Aging Analysis of Open Issues

Every issue has a discovery date and status. You can determine the percentage of issues that are open by the date of discovery. That is, for issues that were discovered in the past week, the percentage is almost 100%. Meanwhile, the issues that were discovered long ago should be solved—leaving a very small percentage. This is the solid chart in Fig. 10.9. A more difficult situation appears in the dashed graph for Project B. Here there is a bump or jump far back in the project. This means that there are a number of issues that have remained unresolved for some time. This will either cause major problems to the project or even cause the project to fail.

Click To expand
Figure 10.9: Aging Chart of Issues over Time

Average Elapsed Time to Resolve Issues

This chart plots the average elapsed time it takes to resolve an issue for all issues discovered up to a specific point in time. Figure 10.10 is an example of this chart. The solid line corresponds to a well-behaved project in which the elapsed time increases as the team, leader, and managers get familiar with solving issues. Then the elapsed time declines until at the end you almost will solve an issue the minute it appears.

Click To expand
Figure 10.10: Average Elapsed Time to Resolve an Issue

Analysis of Open Issues by Impact and Time Urgency

Two factors have not been considered—impact and time urgency. These are subjective, depending on the person who is viewing the issues. Nevertheless, their analysis is useful. Figure 10.11 presents a general chart in which time pressure is the horizontal axis and impact on the project is on the vertical axis. Issue 5 is time urgent, but of low impact. Issue 12 is both time urgent and high impact. It is important. So you should pay attention to the issues in the upper right quadrant.

Click To expand
Figure 10.11: General Chart of Impact and Time Urgency

However, you cannot stop there. While you cannot address all open issues, you can consider those that have less impact, but that are time urgent. This is the lower right quadrant. So if you put this together, you are going to give attention to the issues in the ellipse.

Now let’s consider an example. Figure 10.12 shows the open issues on the chart at a specific time. Figure 10.13 reveals the issues at a later time. Note that focus at the first time was on the issues in the upper right and lower right quadrants. The other issues were left alone. In Fig. 10.13 these issues are removed, but new issues emerged and the position of the other unresolved issues changed.

Click To expand
Figure 10.12: Chart of Impact and Time Urgency at Time 1
Click To expand
Figure 10.13: Chart of Impact and Time Urgency at Time 2

Some specific notes are:

  • Issues 17, 24, and 47 were resolved after the first time and do not show up in the second chart.

  • Issue 36 is still there and didn’t change position over the time.

  • Issue 65 appeared for the first time on the second chart.

  • Issue 8 became critical over time.

  • Issue 19 changed but it did not become critical as yet.

  • Issue 26 appeared as low impact, but high time urgency.

What is going on? Over time the time urgency and impact of specific issues may change. This method gives you a useful way to chart these. It is understandable to management and makes an interesting slide show out of what would normally be a boring and arcane subject.

Overall, how do you use these charts? You should consider these as additional templates for issues analysis. These should be produced for each critical and major international project.

16 times read

Related news

» Issue Analysis
by admin posted on Oct 03,2007
» Issues And Multiple Projects
by admin posted on Oct 03,2007
» Project Status Communications
by admin posted on Oct 03,2007
» A General Process For Managing Issues
by admin posted on Oct 03,2007
» Deal with Issues and Use Experience
by admin posted on Dec 19,2006