 Sections
Syndication |
|
|
|
|
Everything You Must Know
Everything You Must Know
As promised, this section now covers all of the information you
must know going into the exam. It’s highly recommended you create a method to
recall this information.
The 39 Project
Management Processes
Table B-1
shows the 39 project management processes. The intersection of the Knowledge
Area and each stage (Initiating, Planning, Executing, Controlling, and Closing)
describes the activity that happens at that point in the project. For example,
follow the Project Scope Management row and the Controlling column to find Scope verification and change control.
Table B-1: The 39 Project Management
Processes
|
Knowledge Area |
Initiating |
Planning |
Executing |
Controlling |
Closing |
|
Project Integration Management |
|
Developing the project plan. |
Project plan execution. |
Integrated change control. |
|
|
Project Scope Management |
Project Initiation |
Creating and defining the project scope. |
|
Scope verification and change control. |
|
|
Project Time Management |
|
Defining activities, their sequence, and their estimated
duration. Developing the project schedule. |
|
Schedule control. |
|
|
Project Cost Management |
|
Determining the required resources, their estimated costs,
and completing cost budgeting. |
|
Enforcing cost control. |
|
|
Project Quality Management |
|
Planning for quality. |
Adhering to the performing organization's quality assurance
(QA) requirements. |
Enforcing quality control (QC) on the project. |
|
|
Project Human Resources Management |
|
Completing organizational planning and staff
acquisition. |
Ensuring team development. |
|
|
|
Project Communications Management |
|
Creating the Communications Management Plan. |
Distributing the required information to the appropriate
parties. |
Reporting on project performance. |
Completing administrative closure. |
|
Project Risk Management |
|
Completing risk management planning, risk identification,
qualitative and quantitative risk analysis, and risk responses. |
|
Monitoring and controlling risk. |
|
|
Project Procurement Management |
|
Completing the procurement and solicitation
planning. |
Soliciting vendors to participate on the project. Completing
source selection based on defined criterion, and then following-through with
contract administration. |
|
Completing the contract
closeout. |
Magic Project
Management Formulas
Figure B-1 shows the major formulas you should know for
the exam.
EVM Formulas
Figure B-2
shows the EVM formulas you should know for the exam.
Quick Exam
Facts
This section has some quick facts you should be know at a
glance. Hold on, this moves pretty fast.
Organization Structures Organizational
structures are relevant to the project manager’s authority. A project manager’s
authority will vary depending on the organizational structure he’s operating
within. The structures that offer the least power to the highest amount of power
for the project manager are in the following order:
-
Functional
-
Weak matrix
-
Balanced matrix
-
Strong matrix
-
Projectized
WBS Facts The Work Breakdown Structure (WBS) is
the big picture of the project deliverables. It is not the activities that occur
to create the project, but the components the project will create. The WBS helps
the project team and the project manager create accurate cost and time
estimates. The WBS also helps the project team and the project manager create an
accurate activity list. The WBS is an input to five planning processes:
-
Cost estimating
-
Cost budgeting
-
Resource planning
-
Risk Management Planning
-
Activity definition
Project Scope Facts Projects are temporary
endeavors to create a unique product of service. Projects are selected by one of
two methods:
-
Benefit measurement methods These include
scoring models, cost-benefit ratios, and economic models.
-
Constrained optimization Mathematical
models based on linear, integer, and dynamic programming models. (You probably
won’t see this one on the IT Project+ exam as a viable answer.)
The project scope defines all of the required work, and only the
required work, to complete the project. Scope management is the process of
ensuring the project work is within scope and protects the project from scope
creep. The scope statement is the baseline for all future project decisions as
it justifies the business need of the project. There are two types of scope:
Scope verification is the process completed at the end of each
phase and project to confirm the project has met the requirements. It leads to
the formal acceptance of the project deliverable.
Project Time Facts Time can be a project
constraint. Effective time management is the scheduling and sequencing of
activities in the best order to ensure the project completes successfully—and in
a reasonable amount of time. There are some key terms for time management:
-
Lag Waiting between activities.
-
Lead Activities come closer together and
even overlap.
-
Free float The amount of time an activity
can be delayed without delaying the next scheduled activity’s start date.
-
Total float The amount of time an activity
can be delayed without delaying the project finish date.
-
Slack and float These are synonymous;
duration may be abbreviated as “du.”
There are three types of dependencies between activities:
-
Mandatory This hard logic requires a
specific sequence between activities.
-
Discretionary This soft logic prefers a
sequence between activities.
-
External Due to reasons outside of the
project, such as vendors, the sequence must happen in a given
order.
Project Cost Facts There are several methods
for providing project estimates:
-
Bottom-up Project costs start at zero and
each component in the WBS is estimated for costs and then the “grand total” is
calculated. This is the longest method to complete, but it provides the most
accurate estimate.
-
Analogous Project costs are based on a
similar project. This is a form of expert judgment, but it is also a top-down
estimating approach so it less accurate than a bottom-up estimate.
-
Parametric Modeling Price is based on cost
per unit; examples include cost per metric ton, cost per yard, cost per
hour.
There are four types of costs attributed to a project:
-
Variable costs The costs depend on other
variables. For example, the cost of a food-catered event depends on how many
people register to attend the event.
-
Fixed costs The cost remains constant
throughout the project. For example, a rented piece of equipment is the same fee
each month even if it is used more in some months than others.
-
Direct costs The cost is directly
attributed to an individual project and cannot be shared with other projects;
for example, airfare to attend project meetings, hotel expenses, and leased
equipment that is used only on the current project.
-
Indirect costs These are the cost of doing
business; examples include rent, phone, and utilities.
Quality Management Facts The cost of quality is
the money spent investing in training, requirements for safety, laws and
regulations, and steps added to ensure quality acceptance. The cost of
nonconformance is the cost associated with rework, downtime, lost sales, and
waste of materials.
Some common quality management charts and methods include:
-
Ishikawa diagrams These diagrams are also
called fishbone diagrams. They are used to find causes and effects that
contribute to a problem.
-
Flow charts These charts show the
relationship between components and the flow of a process through a system.
-
Pareto Diagrams These diagrams identify
project problems and their frequencies. These are based on the 80/20 Rule: 80
percent of project problems stem from 20 percent of the work.
-
Control Charts These charts plot out the
result of samplings to determine if projects are “in control” or “out of
control.”
-
Kaizen technologies These technologies
make small improvements in an effort to reduce costs and consistency.
-
Just-in-time ordering
This method reduces the cost of inventory but requires additional quality
because materials are not readily available should mistakes occur.
Human Resource Facts There are several human
resource theories you should be familiar with on the IT Project+ exam. They are:
-
Maslow’s Hierarchy of Needs There are five
layers of needs for all humans: physiological, safety, social, esteem, and the
crowning jewel—self-actualization.
-
Herzberg’s Theory of Motivation There are
two catalysts for workers: hygiene agents and motivating agents.
-
Hygiene agents These do nothing to
motivate workers, but their absence demotivates them. Hygiene agents are the
expectations all workers have: job security, a paycheck, clean and safe working
conditions, a sense of belonging, civil working relationships, and other basic
attributes associated with employment.
-
Motivating agents These are the elements
that motivate people to excel. They include responsibility, appreciation of
work, recognition, the opportunity to excel, education, and other opportunities
associated with work other than just financial rewards.
-
McGregory’s Theory of X and Y This theory
states “X” people are lazy, don’t want to work, and need to be micromanaged. “Y”
people are self-led, motivated, and can accomplish tasks.
-
Ouchi’s Theory Z This theory believes the
workers are motivated by a sense of commitment, opportunity, and advancement.
Workers will work if they are challenged and motivated. Think participative
management.
-
Expectancy Theory People will behave based
on what they expect as a result of their behavior. In other words, people will
work in relation to the expected reward of the work.
Communication Facts Communicating is the most
important skill for the project manager. With that in mind, here are some key
facts on communications:
-
The communication channels formula is N(N - 1)/2. N
represents the number of stakeholders. For example, if you have 10 stakeholders,
the formula would read 10(10 - 1)/2 for 45 communication channels. Pay special
attention to questions wanting to know how many additional communication
channels you have based on added stakeholders. For example, you have 25
stakeholders on your project and have recently added 5 team members. How many
additional communications do you now have? You’ll have to calculate the original
number of communication channels, 25(25-1)/2 = 300, and then calculate the new
number with the added team members, 30(30-1)/2 = 435, and, finally, subtract the
difference between the two: 435 - 300 = 135 additional communication
channels.
-
Fifty-five percent of communication is nonverbal.
-
Effective listening is the ability to watch the speaker’s
body language, interpret para lingual clues, and decipher facial expressions for
insight. The next step is to follow these messages with questions for clarity
and to offer feedback. Active listening requires the receiver of the message to
offer clues, such as nodding the head to indicate he is listening. It also
requires the receiver to repeat the message, ask questions, and continue the
discussion if clarification is needed.
-
Communication can be hindered by trendy phrases, jargon, and
extremely pessimistic comments. In addition, communication can be blocked by
noise, hostility, cultural differences, and static among other communication
barriers.
Risk Management Facts Risks are unplanned
events that can affect the project for good or bad. Risks should be identified
as early as possible in the planning process. A person’s willingness to accept
risk is the Utility Function (also called the Utility Theory). The Delphi
Technique can be used to build consensus on project risks.
The only output of the risk planning is the Risk Management Plan.
There are two broad types of risks:
-
Business risk The loss of time and
finances; a downside and an upside may exist.
-
Pure risk The loss of life, injury, and
theft. Only a down side exists.
Risks can be responded to in one of four methods:
-
Avoidance Avoid the risk by planning a
different technique to remove the risk from the project.
-
Mitigation Reduce the probability or
impact of a risk.
-
Acceptance The risk’s probability or
impact may be small enough that it can be accepted.
-
Transference The risk is not eliminated
but the responsibility and ownership of the risk is transferred to another
party; for example, it’s transferred to insurance.
Procurement Facts A Statement of Work (SOW) is
provided to the potential sellers so they can create accurate bids, quotes, and
proposals for the buyer. A bidders’ conference may be held so sellers can query
the buyer on the product or service to be procured.
A contract is a formal agreement, preferably written, between a
buyer and seller. On the exam, procurement questions are usually from the
buyer’s point of view. All requirements the seller is to complete should be
clearly written in the contract. Requirements of both parties must be met or
legal proceedings may follow. Contract types include:
-
Cost-reimbursable contracts require the buyer to assume the
risk of cost overruns.
-
Fixed-price contracts require the seller to assume the risk
of cost overruns.
-
Time-and-material contracts are good for smaller assignments
but can impose cost overrun risks to the buyer if the time by the seller is not
monitored.
-
A purchase order is a unilateral form of contract.
-
A letter of intent is not a contract, but it shows the
intent of the buyer to purchase from a specific
seller.
766
times read
|
|
|
Did you enjoy this article?
(total 0 votes)
|
Comments (0 posted) Please Comment On This Article
|