IT Project+ Exam Objectives
The IT Project+ examination is designed for
information technology (IT) and business professionals involved with IT projects
and business projects with a technology component. The examination is designed
for candidates possessing at least 12 months of cumulative experience in
leading, managing, and directing small- to medium-scale IT projects. IT Project+
examines the business, interpersonal, and technical project management skills
required to successfully manage IT projects and business initiatives with a
technology component.
The skills and knowledge measured by this examination are derived
from an industry-wide job task analysis and validated through an industry-wide
survey. The results of this survey were used in weighing the domains and
ensuring that the weighting is representative of the relative importance of the
content. The exam is in a conventional linear format. There are 80 questions on
the exam and candidates have 90 minutes to complete them. The exam is available
in English only.
The objectives in this appendix are current at the time of this
publication, but you should always refer to the Computer Technology Industry
Association web site at www.comptia.org to obtain the most current version of the exam
objectives as they are subject to change. The following table lists the domains
measured by this examination and the extent to which they are represented.
Response Limits
The candidate selects the option(s) that best completes the
statement or answers the question from four or more response options.
Distracters, or wrong answers, are response options that a candidate with
incomplete knowledge or skills is likely to choose given these choices are
generally plausible responses for the content area. Test item formats used in
this examination are
-
Multiple choice The candidate selects one
option that best answers the question or completes a statement.
-
Multiple response The candidate selects
more than one option that best answers the question or completes a
statement.
-
Drag and drop items The candidate drags a
graphic or text to the correct destination.
Domain 1.0 IT Project Initiation and Scope Definition
This domain requires that the candidate possess the knowledge
to:
-
Identify stakeholder objectives for an IT project and
prepare a high-level scope statement that correctly defines the work required to
achieve those objectives
-
Define high-level business and technical requirements,
outcomes, criteria for success, and stakeholders’ low-level needs and
expectations, including boundaries for project budget, duration, and risk
-
Identify the project roles of stakeholders including the
project manager, project sponsor, and project team members
-
Secure stakeholder/client consensus and obtain approval of
the project charter and preliminary scope documents
1.1. Given a vague or poorly worded customer request
or business need, determine the appropriate course of action in order to 1)
understand a business case scenario and create a project proposal, 2) understand
or analyze a Request for Proposal (RFP) and create a project proposal:
-
Generate and refine a preliminary project concept definition
or statement of work
-
Informally determine the business need and feasibility of
the project
-
Identify project sponsors who will help obtain resources
-
Understand the concept of cost-benefit analysis to justify
the project
-
Obtain formal approval from the project sponsor
-
Confirm management support
1.2. Given the set of criteria that
outlines an enterprise’s minimal requirements for a project charter, together
with stakeholder input, synthesize a project charter, including:
-
Project title and description
-
Project manager
-
Key roles and responsibilities
-
Project objectives and success criteria
-
High-level cost benefit analysis
-
Business case/mission
-
Product/deliverable description, performance criteria, and
enhancement opportunities
-
High-level risk assessment
-
Consensus building
1.3. Identify strategies for building consensus
among project stakeholders. Select an appropriate course of action involving
negotiation or interviewing strategies, meetings, memos, etc.
1.4. Recognize and explain the need to obtain formal
approval (sign-off) by the project sponsor(s) and confirm other relevant
management support to consume organization resources as the project charter is
refined and expanded.
1.5. Given a scope definition scenario, demonstrate
awareness of the need to secure written confirmation of customer expectations in
the following areas:
-
The background of the project (for example, a
problem/opportunity statement, strategic alignment with organizational goals and
other initiatives, why the project is being initiated at this time, etc.)
-
The deliverable from the project (that is, what the product
will look like, be able to do, who will use it, etc.)
-
The strategy for creating the deliverable
-
Targeted completion date and rationale behind that date
-
Budget dollars available and basis upon which that budget
was determined
-
Areas of risks which the project client is or is not willing
to accept
-
The priority of this project as it relates to all the other
projects being done within the organization
-
The sponsor of the project (that is, who will provide
direction and decisions)
-
Any predetermined tools or resources
-
Assumptions that resources will be available as
needed.
1.6. Given a project initiation document (a project
charter or contract), including a confirmed high-level scope definition and
project justification, demonstrate the ability to identify and define the
following elements:
-
The stakeholders, including the primary project client, the
ultimate end users, and any other impacted parties (internal or external to the
organization), their roles and special needs
-
An all-inclusive set of requirements presented in specific,
definitive terms which include:
-
Differentiation of mandatory versus optional
requirements
-
Success criteria upon which the deliverable will be
measured
-
Completion criteria (for example, what needs to be
delivered, such as a fully tested system or a system that’s been live for three
months)
-
Requirements that are excluded from the
project
-
Targeted completion date, including:
-
Relative to a specified start date,
-
Expressed as a specific date (that is, mm/dd/yy), a range of
dates, or a specific quarter and year (3rd quarter 2004)
-
The consequences if that date is not met
-
A milestone chart including any phase reviews, if
appropriate
-
Anticipated budget, including any or all of the
following:
-
Plus or minus tolerance
-
Contingency funds and/or any management reserves, if
negotiated
-
The consequences if that budget is not met
-
Which of the above three criteria—for example, technical
performance (quality), completion date (schedule), or anticipated budget—is the
highest priority to the project client
-
All assumptions made relative to A through E
1.7. Given a project initiation document (a project
charter or contract), including the client’s highest priority between quality,
time, and budget, estimate any or all of the following:
-
The potential impact of satisfying the client’s highest
priority at the expense of the other two
-
The impact of the project on business operations
-
Worse-case scenario targeted completion date, budget, and
quality level
-
Your confidence level in the projected completion date,
budget and prospects for a high-quality deliverable
1.8. Given a project charter or contract including a
statement of work (SOW), recognize and explain the need to investigate specific
industry regulations requirements and contractual/legal considerations for their
impact on the project scope definition and project plan.
1.9. Given a proposed scope definition and based on
the scope components, assess the feasibility of the project and the viability of
a given project component against a predetermined list of constraints,
including:
-
A clearly defined project end date
-
A clearly defined set of monetary resources or
allocations
-
A clearly defined set of product requirements, based on a
thorough decomposition of the system’s hardware and software components
-
Clearly defined completion criteria
-
Clearly defined priorities
-
The relative priority of cost, schedule, and scope
-
Project ownership
-
Mandated tools, personnel, and other resources
-
The requirement that scope will change only per change
control
-
Vendor terms and conditions
-
Company terms and conditions
-
A “best practices” life cycle for this type of project
-
Required reviews of deliverables by stakeholders and
approvals by sponsors
-
RFP procedures, selection criteria, evaluation criteria, and
standards
1.10. Recognize and explain the need to obtain
formal approval (sign-off) by the project sponsor(s) and confirm other relevant
management support to consume organizational resources as the project scope
statement is being developed.
1.11. Given an incomplete project scope definition,
complete or rewrite the definition to 1) reflect all necessary scope components
or 2) explicitly state what is included in the project and what is not included.
Necessary components include:
-
Project size
-
Project cost
-
Projected schedule and window of opportunity
-
Stakeholders, their roles, and their authorities
-
The project manager’s role and authority
-
Completion criteria
-
Methodologies to be followed
-
The scope change control process
-
Mandated tools, personnel, and other resources
-
Industry or government regulations that apply
1.12. Identify the following as
possible elements of a final project scope definition and the circumstances in
which they would be appropriate:
-
A requirements change control process, including how to
request a change, how to analyze the impact of the change, and how to obtain
approval for the additional funds and/or time to implement the
change
1.13. Recognize and explain the need to build
management buy-in and approval into the structure of the project, and describe
strategies for doing so, including:
-
Involving management in up-front definitions of project
concept and charter
-
Involving management in defining and approving project
scope
-
Involving management in reviewing and approving all key
project deliverables as they evolve
-
Providing a role for management as a spokesperson-advocate
for the project, for team member participation, and for the
deliverables
1.14. Recognize the need to obtain a consensus among
stakeholders and to obtain buy-in from the team to proceed to the planning stage
of the project given a high-level estimate of scope, schedule, budget, and
resources.
1.15. Recognize the need to conduct a review meeting
as the project transitions from the initiation phase to the planning phase. The
review would include an assessment of the following:
-
Completion of the project initiation documentation
-
Viability of the business case
-
Achievement of stakeholder consensus
Domain 2.0: IT Project Planning
This domain requires the knowledge and skills to:
-
Define in adequate depth the project
deliverable(s)/product(s) and associated requirements
-
Create a Work Breakdown Structure (WBS)
-
Identify a project strategy and life-cycle
-
Create a schedule
-
Create a list of required resources
-
Perform project cost estimation and create a budget
-
Perform risk analysis and create a risk
-
Create a Communications Management Plan
-
Create a Quality Management Plan
-
Organize a comprehensive, detailed project plan
-
Validate stakeholder expectations
-
Establish change control over the project plan and develop
procedures for updating and/or changing the plan
-
Close out the planning phase
Project Strategy Development and Preliminary Planning
2.1. Demonstrate knowledge of the typical IT project
life cycle and its application to IT projects, including:
-
Phases (requirements, design, build/unit test, integration
test, deploy)
-
The reason for the phases
-
The common deliverables from the phases
-
Target phase transition dates
2.2. Given an approved project
charter, high-level scope documents, and schedule/budget objectives, demonstrate
the ability to create a project management plan that illustrates the
following:
-
Understanding of the roles of stakeholders, what reporting
information each needs, and when it is needed
-
Understanding the risks incurred by not including key
participants during the planning process
-
Knowledge of how to establish a project tracking
mechanism
-
Awareness that a training plan may be necessary
-
Awareness that a procurement plan may be
necessary
2.3. Demonstrate an understanding of the following
estimating concepts, techniques, and issues, including:
-
The concept of bottom-up cost estimates, their purpose, and
the conditions under which they are necessary
-
Standard estimating techniques that can be used to solicit
initial financial budget inputs based on mutual agreeable high-level
requirements
2.4. Given a team-building scenario, including a
scope definition and WBS, identify selection criteria for particular team
members. Demonstrate the ability to ask interview questions that will assist the
team selection process. Assume project organization includes:
-
Business
-
Leadership
-
Administration
-
Technical
-
Stakeholders
2.5. Identify methods for resolving disagreements
among team members when evaluating the suitability of deliverables at each point
in their evolution.
Requirements Analysis
2.6. Given a project description/overview and a list
of the project business and technical requirements, do the following:
-
Decide if the project is defined well enough to achieve a
measurable outcome and metrics for success
-
Determine if the requirements include the necessary range of
inputs (assumptions, expectations, technical issues, industry issues, etc.) in
order to validate the input given and gaps related to scope
-
Distinguish any input provided which does not relate to the
project at hand in order to achieve greater focus
-
Recognize whether the list of requirements is complete,
accurate, and valid enough to move on to the planning step
-
Give a situation where the project outcomes are not possible
to verify
-
Recognize the role poorly detailed requirements,
assumptions, and expectations play
-
Identify the high-level value of the project to the sponsor
and end users
-
Describe the role of project value and its importance to
individual and team effectiveness
2.7. Describe the goals of a useful project
requirements review with the client (for example, verify a mutual understanding
of client’s product delivery, product performance, and budget requirements,
etc.) and describe when it is important to have such reviews.
2.8. Given the client’s approved project
requirements and the input of stakeholders, decompose these requirements into
business and functional requirements while maintaining traceability within
strict configuration control.
Create WBS
2.9. Given a project planning scenario, demonstrate
an understanding of and the ability to develop a phase-oriented WBS with high
detail for an early phase and with low detail for later phases by:
-
Identifying elements (phases) likely to require iterative
planning
-
Explicitly deciding to provide for iteration in the project
plan (for example, scope approval, plan approval, project design, final
deliverable turnover, etc.)
2.10. Given a scenario involving tasks, resources
(fixed or variable), and dependencies for a multiphase IT project, demonstrate
knowledge of the standards for creating a workable WBS by:
2.11. Recognize and explain the need to obtain:
-
Consensus among all stakeholders regarding project
deliverables and other elements of the WBS
-
Formal approval (sign-off) of project sponsor(s) regarding
project deliverables and other elements of the WBS.
2.12. Given a project scenario with many phases and
activities, set realistic, measurable milestones, and demonstrate an
understanding that measurable targets are required to determine if the project
is proceeding on time and within budget.
2.13. Given a set of specific milestones and their
descriptions, specify entry and exit criteria for each.
Perform an Estimation
2.14. Demonstrate the ability to create an activity
cost estimate given:
2.15. Demonstrate the ability to create an activity
time estimate (in units of time) given:
2.16. Recognize and explain the difference between a
project cost estimate, effort estimate, and time estimate.
Create a Schedule
2.17. Identify and list the components needed to
generate a workable project schedule. Demonstrate the ability to create
appropriate project schedules, which meet the approved project start and finish
dates, given the following information:
-
A detailed list of project deliverables (both interim and
finished)
-
A detailed estimate of project tasks
-
A list of activities and phases
-
A detailed estimate of the time and resources required to
complete all project tasks
-
Information about the preferences of the project team
regarding schedule formats
2.18. Given a scenario with
necessary project documents, and given enterprise holiday and individual
resource calendars, demonstrate the ability to develop a project schedule by
doing the following:
-
Define and sequence project tasks, activities, and phases
that are needed to bring about the completion of a given interim or finished
project deliverables
-
Estimate durations for project tasks, activities, and
phases
-
Estimate work effort for project tasks and assignments
-
Specify resources required for the completion of each
phase
-
Identify the project critical path
2.19. Demonstrate the ability to identify project
team organization roles and responsibilities required for the execution of the
project, including:
-
The role of the customer (sponsor) of the project as it
relates to the project manager’s role
-
The major skills required in the project team
-
The type of team structure; for example, part-time matrix,
full-time matrix
-
Confirm the role of the project manager, including any or
all of the following:
-
Responsibilities, accountability
-
Authority: formal and informal
-
Percentage of time available to this project
-
Performance appraisal process relative to this
project
2.20. Demonstrate the ability to assign resources to
the schedule by:
Create a Budget
2.21. Given a project scope, timeline, cost, project
team, and dependencies, demonstrate the ability to:
-
Create and manage a high-level (top-down) budget based on
assumptions/estimates
-
Identify and budget the level, cost, and duration of
resources and dependencies (internal and external)
-
Create and manage a detailed bottom-up budget containing
actual/ scheduled expenses
-
Identify, implement, and budget all project trade-offs while
understanding their implications and impact
-
Install and maintain systems for tracking budgetary expenses
against the plan based on the existing enterprise systems
-
Align the budget with the spending plan of the
organization
Create a Quality Management Plan
2.22. Demonstrate an understanding of the components
of a project quality management plan (for example, measured quality checkpoints,
assignments for architectural control, systems test, and unit tests, user
sign-off, etc.)
2.23. Demonstrate the skills to
develop a quality plan that assures:
-
Awareness of the need to develop a test plan and defect
tracking procedure that ensure appropriate testing steps, defect resolution, and
documentation steps occur during the project life cycle.
-
A configuration management exists that ensures:
-
Phase deliverables are reviewed and inspected for
completion, defects are removed, and issues are resolved prior to acceptance
-
Documented sufficiency criteria exist for the exiting of
each phase
-
A change control process exists for all technical
environments
-
A requirements management process exists
-
Formal customer acceptance and sign-off is obtained at
appropriate points
Create a Risk Management Plan
2.24. Demonstrate the ability to perform risk
assessment and mitigation by doing the following (given a scenario including the
appropriate project documentation):
-
Identify and prioritize the most important risks that will
impact the project
-
Evaluate the severity of the risks to successful completion
of the project
-
Identify risks contained on a project’s critical path and
identify procedures to reduce potential impacts on schedule
Create a Communication Plan
2.25. Demonstrate the ability to create a project
communication plan that clearly indicates what needs to be communicated during a
project, to whom, when, and how (using formal, informal approaches).
Organize a Comprehensive Project Plan and Close Out the
Planning Phase
2.26. Identify the components/documents of an
adequate project plan and explain the function of each. Components include:
-
Table of contents
-
Overview/executive summary
-
Sponsors
-
Team members
-
Requirements
-
Scheduled tasks (WBS)
-
Expected resources
-
Environmental issues
-
Business and technical requirements
-
Implementation plans
-
Support plans
-
Training plans
-
Document (plan) location and revision control
2.27. Identify the steps involved in organizing a
comprehensive project plan and using it to close out the planning phase of a
project, including:
-
Assembling all project planning elements (estimates of
deliverables, time, costs, etc.)
-
Creating an outline or table of contents for the
comprehensive project plan
-
Reviewing the outline of the comprehensive project plan with
sponsor and key stakeholders, obtaining feedback and concurrence, and revising
as needed
-
Writing the comprehensive project plan by integrating all
planning elements according to the outline and creating a full document with
transitions, introductions, graphics, exhibits, appendices, etc., as
appropriate
-
Circulating the comprehensive project plan to all
stakeholders
-
Obtaining top management support of the comprehensive
project plan by making certain it reflects their concerns and that they have had
an opportunity to provide input
-
Conducting a formal review of the comprehensive project plan
in which stakeholders have an opportunity to provide feedback
-
Adjusting the comprehensive project plan based on
stakeholder feedback
-
Obtaining formal approval (sign-off) of the comprehensive
project plan by sponsor(s)
2.28. Demonstrate knowledge of how
to set performance baselines for:
2.29. Demonstrate knowledge of the need to create
change management procedures for the project plan.
2.30 Be able to identify project performance
indicators that will be used to monitor and control performance during
execution.
2.31. Be able to secure staffing commitments and
resolve staffing issues.
2.32. Recognize the need to conduct a review meeting
as the project transitions from the planning phase to the execution and
coordination phases. The review includes an assessment of the following:
-
Completion of the project planning documentation
-
Resolution of all planning issues
-
Continued viability of the business case
-
Alignment of stakeholder expectations with the
plan
Domain 3.0: IT Project Execution, Control and
Coordination
This domain requires the candidate to demonstrate knowledge and
skills in:
-
Project monitoring, tracking, and performance reporting
-
Interpreting project performance indicators and identifying
variances from plan
-
Taking corrective action
-
Updating the plan and replanning by project phase
-
Issue tracking and issue resolution
-
Risk tracking and risk removal/mitigation
-
Change control
-
Quality management
-
Team management, coordination, and communications
-
Resource management
3.1 Identify the following as tasks that should be
accomplished on a weekly basis in the course of tracking an “up and running”
project.
3.2 Given a scenario with a set of project
performance indicators, demonstrate the ability to recognize when performance
problems are occurring on the project and determine if/when corrective
action/recovery needs to occur.
3.3 Given a scenario with
updates/changes made to the project plan, demonstrate the need to check for
impact on:
3.4 Given a scenario involving a project with a
schedule delay, choose an appropriate course of action.
3.5 Given an approved project and a status report
scenario containing a significant variance from plan (for example, excessive
overtime, purchased items more expensive than a anticipated, etc.), do the
following:
-
Clearly identify the reason for the variance
-
Determine the impact on the schedule and budget and the
effect on stakeholders
-
Determine if scope creep is occurring
-
Identify options for corrective action
-
Identify options for absorbing part or all of the increase
in the overall budget (if any)
-
Identify stakeholders who must be notified or must give
approval to a change of schedule or budget and develop a plan for advising them
of the change, the rationale for the change, and the consequences if not
approved
3.6 Given a scenario in which a vendor requests a
two-week delay in delivering its product, explain how to do the following:
-
Negotiate a lesser delay by identifying things the vendor
might do to improve its schedule
-
Clearly identify the impact of the negotiated delivery on
the project scope and critical path
-
Present this impact to the appropriate
stakeholders
3.7 Given a scenario in which there is a
disagreement between a vendor and your project team, identify methods for
resolving the problem.
3.8 Identify issues to consider when trying to
rebuild active project support from a wavering executive (for example, the need
to identify the source of doubts, interpersonal communications skills that might
be employed, the need to act without creating negative impact, the need to
identify and utilize various allies and influences, etc.). Given a scenario
involving a wavering executive, choose an appropriate course of action.
3.9 Identify issues to consider when trying to
obtain approval of a changed project plan that is still within expected budget,
but has a schedule that extends outside of the original baseline end date.
3.10 Define and explain Estimate to Complete (ETC),
Estimate at Complete (EAC), and Budget at Completion (BAC).
3.11 Demonstrate the ability to track the financial
performance of a project given the financial management baseline and data on the
actual performance of the project. Demonstrate:
-
The need to identify and understand proposed changes from
plan
-
The need to be able to justify and sell the changes
-
The need for alternative courses of action if the plan isn’t
accepted, etc.
Change Control
3.12 Given an approved project plan and a specific
scope deviation (for example, design, schedule, or cost change, etc.),
demonstrate your ability to:
-
Identify the cause(s)
-
Prepare a status report for the user identifying problems
and corrective action
-
Determine the impact of the deviation on the scope of the
project
-
Quantify the deviation in terms of time, cost, and
resources
-
Distinguish between variances that will affect the budget
and duration and those that will not
-
Determine and quantify at least one possible alternative
solution that has less impact but requires some scope compromise
-
Distinguish between those variances that should be elevated
to the sponsor and those that should be handled by the project manager and
team
-
Develop a plan to gain stakeholder approval
-
Use a change order
3.13 Identify and justify the following as
conditions for initiating a change control process:
3.14 Given scenarios involving requests for changes
from sponsors, team members, or third parties, recognize and explain how to
prevent scope creep.
3.15 Recognize and explain the
importance of communicating significant proposed changes in project scope, and
their impacts, to management, and getting management review and formal
approval.
Quality Management
3.16 Identify and explain strategies and
requirements for maintaining qualified deliverables given a large project with
many team members at multiple locations (for example, communication standards
work standards, etc.).
3.17 Recognize and explain the importance of testing in situations
where tasks are being performed by both project team members and third
parties.
3.18 Identify and explain strategies and
requirements for assuring quality during the turnover phase (for example, user
docs, user training, helpdesk training, support structure, etc.).
3.19 Identify and explain strategies and
requirements for assuring quality of deliverables and meeting sufficiency
standards during each phase.
3.20 Recognize the need for controlling changes on
the configuration of the project deliverable and explain its importance.
3.21 Recognize the relevance of the organization’s
Quality Policy to project quality.
Team Management
3.22 Identify effective strategies for providing
timely performance feedback to team members.
3.23 Demonstrate an understanding of
how to effectively manage disgruntled team members so that team performance is
not adversely affected.
3.24 Demonstrate an understanding of how to
recognize individual team member performance issues and to identify effective
strategies for corrective action.
Resource Management
3.25 Given an initial high-level scope, budget, and
resource allocation, demonstrate an understanding of the need to investigate the
aspects of the project that could be modified to improve outcomes (that is, find
out what is negotiable, prepare to negotiate). Provide evidence of the following
competencies:
-
The ability to recognize that individual project team
member’s needs must be addressed to the extent that project activities can be
modified without significant impact on final scope, budget, quality, or
schedule
-
The ability to evaluate alternatives to a scope change
request that stakeholders may find acceptable
-
The ability to recognize which aspects (schedule, budget,
quality) of the project are most important to the stakeholders and be able to
propose trade-offs during the project that can be made to meet or exceed those
aspects
-
The ability to identify all of the individuals and groups
with which you will need to negotiate during the life of the project (sponsors,
vendors, users, internal and external service organizations, other project
teams, project team members, finance/accounting, etc.)
3.26 Given a project scenario, demonstrate the
ability to resolve a resource availability (staffing) issue requiring escalation
to the project sponsor and senior level stakeholders.
Coordination
3.27 Given a project scenario during the
implementation phases, demonstrate the understanding of the need to organize and
effectively run meetings.
3.28 Given a project team meeting scenario in which
a decision must be made with imperfect information, demonstrate the knowledge of
problem solving techniques to help the team through a decision making
process.
3.29 Given a project team meeting scenario,
demonstrate an awareness of the need to provide direction and clarify work
instructions to team members.
3.30 Given a project team meeting scenario where the
project is behind plan, demonstrate an awareness of the need to:
-
Identify an accountable team member
-
Clarify the root cause of the problem causing the delay
-
Develop a strategy for corrective action
-
Implement the corrective action strategy
-
Follow up to check on results
3.31 Given a project scenario where intra-team
communication is inadequate, demonstrate the ability to improve communication to
an appropriate level.
Risk and Issue Management
3.32 Given a project team meeting scenario,
demonstrate the knowledge to review an issue log with team members and secure
closure of issues.
3.33 Demonstrate the ability to
prioritize issues by severity and impact on quality.
3.34 Demonstrate an understanding of how to determine if/when
planned risks have materialized and how to implement planned risk mitigation and
removal strategies.
3.35 Demonstrate the ability to prioritize risks by
severity and impact on quality.
3.36 Demonstrate the ability to remove/mitigate a
project risk.
3.37 Demonstrate an understanding of how to report
to the project sponsor that a project is in jeopardy and how to report
corrective action strategies that are underway.
3.38 Demonstrate an understanding of how to
determine when a project should be prematurely terminated.
Relationship Management with Business (Client)
Organization
3.39 Recognize potential organizational and
political barriers inhibiting an effective working relationship between the IT
organization and the client / business organization.
3.40 Demonstrate an understanding of methods to
develop and maintain an effective working relationship during projects between
the IT organization and the client/business organization.
Domain 4.0: Project Closure, Acceptance, and Support
4.1 Recognize and explain the value of conducting a
comprehensive review process that identifies the lessons learned and evaluates
the planning, organizing, directing, controlling, execution, and budget phases
of the project, identifying both the positive and negative aspects in a written
report.
4.2 Recognize the need to plan to transfer the
project deliverable to support and maintenance and to budget for these
resources, including help desk.
4.3 Recognize the need for acceptance testing (user
acceptance testing, factory acceptance testing, site acceptance testing) of the
project deliverable.
4.4 Recognize the need to obtain formal customer
sign-off on the project deliverable and hand-off to the customer.
-
Close out meeting with customer/sign-off on statement of
work
-
Begin support/maintenance
-
Change control to additional scope
-
Formally turn over deliverable to the customer
4.5 Recognize the need to complete project
documentation, secure approvals, and archive/store documentation
appropriately.
4.6 Recognize the need to close out contracts
and sign-off for vendors.