 Sections
Syndication |
|
|
|
|
Coordinating WBS Components
Coordinating WBS Components
Some project managers would recommend that you continue to
break down each task until you cannot break down the activity anymore. However,
conventional wisdom contradicts a continual decomposition of any activity, as it
eventually leads to units of work that are too small. While some control over
the work to be completed is required, a project manager needs to put faith in
her team to complete the tasks necessary to finish the job.
As a rule, find an acceptable amount of time that will serve as
the smallest increment of work. For example, with a small project, you may only
break work down into days. With a larger project, you may choose to break work
down into weeks. The key is to not continue to break down each activity into
tiny, unmanageable tasks. A heuristic you can rely on is the “8/80 Rule.” The
8/80 Rule suggests that the smallest work package take no more than 80 hours of
time to complete—or no less that eight hours to complete. While this rule can
apply to most projects, it’s not always applicable. For example you may have a
work package that represents a sub-project or part of your project that you’ll
be outsourcing to a vendor. The group completing the activities will likely
decompose these work packages into their own WBS.
Why You Need a
WBS
You may be tempted to skip the process of creating a
WBS—especially on smaller projects. Don’t yield to that temptation. By creating
a WBS, even on small projects, a project manager can accurately predict several
things:
-
A WBS defines the required work to
complete the project. How many times have you started any project only to
uncover activities that you had totally forgotten about? Or worse, realized that
a component was needed that didn’t exist and had to be created before your
project could continue? A WBS ensures that a project manager knows all of the
required work for the project to be complete.
-
A WBS creates a sense of urgency. By
creating a WBS, a project manager and his team are working toward the project
deliverables. Because the WBS is broken down at its lowest level into work
packages—and the activity is derived from the work packages—the tasks can then
be assigned start and end dates The WBS is needed to ensure proper scheduling
and sequencing for the identified activities to create the project deliverables.
The project can maintain its momentum—and its schedule—if all members complete
their tasks on time. A WBS allows a project manager to track the success or
failure of team members based on the completion of activities, which in turn
creates the deliverables the WBS identifies.
-
A WBS can help prevent scope creep.
When management and departments try to add new features for an existing
project, a WBS can ward them off. Because a WBS is a baseline that maps out each
activity on the road to completion, it becomes easier for a project manager to
rule out additions and new features to a project that has already started. It is
possible, however, to add new features to a WBS, but the schedule will have to
be adjusted to reflect the new additions, as will the budget.
-
A WBS provides control. As a project
manager, you may be in charge of several different IT projects. A WBS can allow
you to graphically view the status of any project and how progress is being
made. You can easily hone in on a particular phase, work unit, or task and make
adjustments, counsel team members, or adjust the schedule as needed. Control is
good.
-
The WBS is the scope baseline. Work
that is not in the WBS is not in the project. It provides a point of agreement
between the project manager, the customer, the sponsor, the team members, the
vendors, and other stakeholders on what is in the project, and what is not in
the project.
Examining a Sample
WBS
Before you get into the inner workings of creating a WBS,
take a moment and examine an existing WBS. Figure 5-2 is a WBS created in Microsoft Visio. This
WBS is for a fictional company named Donaldson Investments and Holdings. The
project is an implementation of a new mail server and the mail clients on all of
the workstations.
In this example, only the work has been identified; the project
manager has not yet assigned the tasks to team members. In addition, the task
durations have been identified here, but they would not be identified in a true
WBS. This WBS was created in Microsoft Project and the file is saved on the
CD-ROM under the name Donaldson if you would like to examine it more closely.
It is difficult to see the progression of work in
an outline form as provided in this example. Figure 5-3 shows the work in Microsoft Project. Project
allows you to see your project through a Gantt chart. This chart displays the
intersection of dates until completion and the tasks within a project. Henry
Gantt, an engineer and social scientist, invented this method of tracking
deliverables in 1917.
1843
times read
|
|
|
Did you enjoy this article?
(total 0 votes)
|
Comments (0 posted) Please Comment On This Article
|